Construction Update: Hardwick STP PC23(1)


Hardwick Class 1 VT 14/VT 15 Paving Project

DATE: Friday, April 22, 2022

TRAFFIC IMPACT AND DURATION: Monday, April 25 through Friday, April 29, between the hours of 6:00 a.m. and 6:00 p.m., motorists should expect intermittent shoulder closures along U.S. Route 14 (VT 14) and Vermont Route 15 (VT 15) within the project area in Hardwick. 

Motorists are reminded to stay alert and slow down through the work zone.

CONSTRUCTION ACTIVITIES: Next week, crews will be on-site completing preparatory work including the installation of road construction signage, clearing and cleaning up of the construction area, and project set up.

Milling operations are anticipated to begin starting the week of Monday, May 2. This work is weather dependent.

LOCATION: The Hardwick Class 1 VT 14/VT15 Paving Project is located on VT 14 and VT 15 in the Town of Hardwick. The project includes approximately 1.7 miles of VT 14 bounded by its intersection with Buffalo Street to the south and just northwest of its intersection with Craftsbury Road and approximately 0.3 miles of VT 15 bounded by its intersection with VT 14 extending just east of Glenside Avenue near the Inn by the River. 

PROJECTED COMPLETION: Fall 2022